Bid bond vs performance bond in Canada
Two different bonds at two different stages: the bid bond answers 'are you serious about this bid?', the performance bond answers 'can you actually finish the work?'.
Bid bond — the competition stage
A bid bond is submitted with your bid and guarantees entry into the contract: if you win and refuse to sign, or fail to deliver the required final security, the buyer claims the bond to re-tender or award to the next bidder. The standard Canadian form is CCDC 220, whose 2024 edition carried forward the 10%-of-bid-price standard set in 2002; buyer requirements commonly range from 5% to 15%. The bond is held by the buyer — under the federal Government Contracts Regulations (SOR/87-402, s. 12), a contracting authority must hold any bid bond it receives until the terms of the security are fulfilled — and released once you sign and provide the performance security, or when the bid validity period (typically 60–90 days) ends.
Performance bond — the delivery stage
A performance bond is issued at contract award and backs actual completion: if the supplier defaults, the surety can complete the work, arrange a substitute contractor, or pay the owner up to the bond limit. The standard form is CCDC 221, and the face value is typically 50% of the contract value for Canadian public-sector construction. The premium — estimated at 0.5–1.5% of contract value by Canadian surety brokers (BidFit, 2026) — is paid once at execution and covers the construction period plus a warranty period.
The third bond contractors forget: labour & material payment
Most government construction tenders require three bonds, not two. A labour and material payment bond (CCDC 222) guarantees the contractor pays subcontractors and suppliers, and is also typically set at 50% of contract value. Sureties usually quote the performance and payment bonds together as a single combined premium under the same underwriting, so it is rarely a separate purchasing decision.
What each bond costs
For the bid bond: a standalone premium estimated at 1–3% of face value (often flat $250–$750 for SMB-sized contracts) or an annual bond facility fee, typically $1,500–$2,500, that covers unlimited tender bonds for the year. For the performance and payment bonds: a combined premium estimated at 0.5–1.5% of contract value, paid once. All figures are Canadian surety-broker market estimates (BidFit, FCA Insurance, 2026), not regulated rates. Estimate the numbers for your bid in our bid bond calculator, and see how much a bid bond costs for the full pricing model.
Frequently asked questions
What is the difference between a bid bond and a performance bond?
A bid bond is submitted with your bid and guarantees you will enter into the contract if you win; a performance bond is issued at contract award and guarantees you will complete the work. In Canada they are issued on standard CCDC forms — CCDC 220 for the bid bond, CCDC 221 for the performance bond — and most public-sector construction tenders require both.
How much is a bid bond vs a performance bond?
Bid bonds are typically 10% of the bid price (CCDC 220 standard; requirements can range 5–15%). Performance bonds are typically 50% of the contract value (CCDC 221). Cost-wise, Canadian surety brokers estimate bid bond premiums at 1–3% of face value (often flat $250–$750 for SMBs) and performance bond premiums at 0.5–1.5% of contract value, paid once at award — market estimates, not regulated rates.
What is a labour and material payment bond?
A labour and material payment bond (CCDC 222) guarantees the contractor pays its subcontractors and suppliers. It is typically set at 50% of contract value like the performance bond, and most Canadian government construction tenders require all three bonds. Sureties usually quote the performance and payment bonds together as a single combined premium.
Do government tenders require both bonds?
Most Canadian public-sector construction tenders require the bid bond at submission and then the performance bond (plus the labour and material payment bond) at award. Under the federal Government Contracts Regulations (SOR/87-402, s. 12), a contracting authority must hold any bid bond, payment bond or performance bond it receives until the terms of the security are fulfilled.